Sanitary Authority Sees Cost Increase West Washington Street Project ↗
Bradford Sanitary Authority’s share of sewer relocation costs associated with PennDOT’s West Washington Street corridor project has increased by more than $53,000, bringing its anticipated contribution to $481,241. During its November meeting, the authority learned sanitary sewer relocation costs came in 12% higher than anticipated, an increase of $212,966 that brings the overall cost of sanitary sewer infrastructure replacement to nearly $1.93 million. The project, first reported by The Era...